Tawesco Welding Shop Modernization

One hall, three years of work, an investment of CZK 17 million. We are transforming one of Tawesco's largest halls. The heavy welding shop is undergoing a modernization that will streamline production both spatially and logistically, preparing the facility for higher production capacities.

o.JPG

The new welding facility will allow us to increase production for existing customers while gaining greater flexibility for new projects. In this hall, we weld large structural components such as frames, chassis structures, and other weldments for agricultural, forestry, and material handling equipment.

NEW WELDING SHOP – FEWER DETOURS, MORE OUTPUT

We are relocating machines and robots, removing original barriers, building new staircases, and installing new cranes. We have also created a new entrance and new handling routes.

  • We are establishing clear corridors for forklifts, which will improve material flow and ensure smoother production.
  • We are increasing safety. The hall will feature separate pathways for pedestrians and handling equipment, and we are building a second main transport artery.

The modifications are being carried out in stages during full operation, so production can continue uninterrupted. This reconstruction is part of a long-term investment plan. Over the past five years, we have invested more than CZK 1 billion into the modernization of TAWESCO.

9. 3. 2026 Investments, Facts

This website uses cookies.

We use cookies to personalize content and ads, provide social media features and analyze our traffic. We also share information about the use of our site with our social media, advertising and analytics partners. They may use the data together with other information they collect about you while using their services.